Program schedule — risk

Four 10-week PIs overrun the Feb 2027 deadline

The full program needs 40 weeks against ~38 weeks of runway — PI 4 lands late.

PI 1
15 Jun – 21 Aug 26
5 sprints
PI 2
24 Aug – 30 Oct 26
5 sprints
PI 3
2 Nov – 8 Jan 27
5 sprints
holiday dip
PI 4
11 Jan – 19 Mar 27
5 sprints
≈ 3 wks over

↑ end Feb 2027 deadline falls inside PI 4

Runway from today
~38 weeks
Needed · 4 × 10 wks
40 weeks
Gap
PI 4 lands ~3 wks late

Options to close the gap

AShorten to 9-week PIs

4 sprints + a short IP each. 4 × 9 = 36 wks — fits with slack, costs ~1 build sprint per PI.

BDescope to fast-follow

Hold 10-week PIs; defer mobile or non-critical web to a release after Feb 2027.

CMove the date

Keep scope & cadence; the only lever that doesn't cut delivery capacity.